Around Town: Progress Report on John Hart Dam in Campbell River

November 2, 2016

Stephen Watson of BC Hydro has provided an update to the John Hart Dam project in Campbell River. Upstream of the dam, crews continue with the concrete work for water intake and maintenance gates.

This photo shows construction work in the Powerhouse cavern at the site of the John Hart Dam Generating Station Replacement Project.

This photo shows construction work in the Powerhouse cavern at the site of the John Hart Dam Generating Station Replacement Project.

Rock breaking and shear-line drilling is being used to create a trench for the low-level outlet that will connect the downstream side of the intake to the river and provide water flow down Elk Falls Canyon.

About 50% of the Phase 1 structural concrete work in the powerhouse is complete. In September, a peak of about 420 people were working on the project in Campbell River. Job totals will now slowly diminish to completion. For more information and to see some onsite pictures, visit this link.